The Municipality of Kincardine has awarded its 2023 hot mix paving contract to EC King Contracting.
Municipal staff has directed the council to award the contract for $653,198 with HST.
EC King was selected as they were the lowest bid for the work to be done.
As a part of the 2023 Capital Budget Plan, approximately 6 km of Concession 11 has been included for resurfacing and culvert replacement with a total budget of $875,000.
Crews will also be doing ditching and gravel with the project.